Road Closures and Alerts

Park Avenue- Sidewalk Improvements 

Work is underway to construct portions of curb, gutter and sidewalk along Park Avenue, between Van Buren Street and Dranesville Road.  Flaggers will be onsite to guide motorists through the work zone.  Work hours will be 7am - 5pm weekdays.  Weather permitting, the project is scheduled for completion in mid-November.

Lynn Street 

Beginning the week of June 19th, crews will be working to replace brick paver crosswalks and sidewalks along Lynn Street, between Center Street and Station Street.  The Farmer's Market and Friday Night Live events will not be affected.   

Bready Park Soccer Field

Beginning May 1st, work to convert the Bready Park soccer field from a grass to synthetic turf will begin.  Contractors will begin work weekdays at 7:00 a.m. and weekends at 8:00 a.m.  Weather permitting, the work is expected to be completed within 90 days.

Junction Square - Lane Closures - Utility Work on /Monroe Street

Utility work in the right of way - Expect lane closures between 9am and 4pm on Monroe Street, between Pine Street and Elden Street. Contractor's typical work hours will be 7am – 4pm Monday – Friday. Weather permitting, work should be completed by the end of May. Motorist should expect delays and use alternate route if possible. Flaggers will be on site to help guide motorists through the construction zone.

Downtown Streetscapes Project

The Historic Downtown Herndon Streetscape – Phase II project will begin the week of April 10, 2017 and construction is anticipated to last for approximately five months. Elden Street between the intersections of Station Street and Monroe Street will be impacted during construction as will Spring Street between the intersections of Elden Street and Locust Street. The contractor’s typical working hours will be 7:00 AM to 5:00 PM Monday - Friday. During construction, it is anticipated that two-way traffic will be maintained through the construction zone at all times with the exception of the potential closure of Spring Street between Elden Street and Locust Street.  Access to properties may be temporarily unavailable for short periods of time during construction.   

Traffic Counts 

Beginning the week of April 24th, VDOT will be performing traffic counts in various locations throughout the town.  Weather permitting, work should be completed by June 23rd.

Utility Work along Herndon Pkwy - between Elden Street and Spring Street

Over the next few months, contractors will be working at the intersections of Grove/Van Buren and along Herndon Parkway between Elden Street and Spring Street. Single lane closures may be required periodically during work hours of 9am and 3pm.

Concrete Replacement and Paving Operations

The concrete replacement and asphalt repaving project is planned annually to improve the safety of the town streets.  Concrete and Paving schedules are subject to inclement weather delays.

 

 

  • DPW Projects (click project below to expand)

    • Design - Van Buren Street Improvements

    • Design - Center Street and Elden Street Improvements

    • Downtown Projects

    • Design - Bus and Car Bays for Herndon Metro Station North Side Access

    • Design - Herndon Parkway/Van Buren Intersection

    • Design - Sterling Road Sidewalk Improvements

    • Design - Park Avenue Sidewalk Improvements